The Boldt Company v. Black & Veatch Construction, Inc.

Federal 7th Circuit Court
Civil Court
Breach of Contract
Citation
Case Number: 
No. 25-2003 & 25-2070
Decision Date: 
July 8, 2026
Federal District: 
N.D. Ill., Eastern Div.
Holding: 
Affirmed in part, reversed in part, remanded.
Judge: 
KIRSCH

Plaintiff filed a lawsuit alleging breach of contract and defendant filed a counter-complaint also alleging breach of contract after plaintiff, who was hired by defendant as a subcontractor for the assembly of a windfarm, fell behind schedule. The district court granted summary judgment to the defendant by finding that plaintiff breached the agreement by failing to perform on schedule, but a jury awarded only nominal damages after a trial on damages only. Both parties appealed, alleging errors. The Seventh Circuit affirmed the jury verdict and affirmed in part and reversed in part the grant of summary judgment, and remanded for further proceedings. (SCUDDER and TAIBLESON, concurring)