Construction Law

Construction Law

Senate Bill 1971

Topic: 
Mechanics Lien Act
(Althoff, R-Crystal Lake) requires that the work be done or the material furnished within three years from the commencement of the work or the start of furnishing the material for owner-occupied property to obtain a lien. For any other property, it is five years. On second reading in the Senate.

Construction Law

The mission of the ISBA Section on Construction Law


Rojas Concrete v. Flood Testing Laboratories

Illinois Appellate Court
Civil Court
Negligence
Citation
Case Number: 
No. 1-09-2300
Decision Date: 
Wednesday, December 15, 2010
District: 
1st Dist.
Division/County: 
Cook Co., 3d Div.
Holding: 
Affirmed.
Justice: 
QUINN
Conrete subcontractor company sued concrete testing company for negligently testing concrete it had poured at UIC construction site, claiming monetary losses for subcontractor being required to remove concrete by UIC. Court properly dismissed complaint, as Plaintiff failed to allege a duty owed it by Defendant, and the voluntary undertaking doctrine, which generally requires a showing of bodily harm, does not extend to purely economic losses. (NEVILLE and MURPHY, concurring.)

Parkway Bank and Trust Company v. Meseljevic

Illinois Appellate Court
Civil Court
Mechanic's Liens
Citation
Case Number: 
No.1-09-3396
Decision Date: 
Tuesday, December 7, 2010
District: 
1st Dist.
Division/County: 
Cook Co., 2d Div.
Holding: 
Affirmed.
Justice: 
KARNEZIS
Plaintiff bank filed foreclosure action as to construction mortgage and sale of underlying real estate (40-unit commercial condominium project). Electrical subcontractor filed counterclaim asserting priority of its mechanic's lien. Court did not err in denying motion to approve late filing of brief in response to motion for judgment on the pleadings, and in denying party participation in oral argument, as no reason for lateness was provided, and motion was unsupported by affidavit. Electrical work was done by subcontractor, rather than by contractor, as it contracted with and performed work for a contractor rather than for the property owner; thus, it was required to provide notice of its lien to the known mortage lender. Subcontractor's lien was invalid as to that lender as it failed to provide it with notice as required by Section 24 of Mechanics Lien Act. (CUNNINGHAM and CONNORS, concurring.)

Mondschein v. Power Construction Company

Illinois Appellate Court
Civil Court
Contribution
Settlement
Citation
Case Number: 
No. 1-09-2278
Decision Date: 
Tuesday, September 28, 2010
District: 
1st Dist.
Division/County: 
Cook Co., 2nd Div.
Holding: 
Affirmed in part and reversed in part; remanded with directions.
Justice: 
THEIS
Plaintiff was injured at construction site on Loyola University building project, and sued general contractor, which filed third-party complaint for contribution against Plaintiff's employer, a steel subcontractor. Plaintiff settled with general contractor for $2.67 million and assignment of counterclaim against steel subcontractor. Jury apportioned liability of steel subcontractor at 35%, and entered judgment for it for 35% of $2.67 million. Court properly denied motion to dismiss where Plaintiff presented evidence to obviate defects in assignment of third-party claim for contribution, that insurers agreed to assign to Plaintiff any subrogated right of contribution. Plaintiff has right to assignment of contribution for amount of subcontractor's actual loss, which is amount not covered by its insurer. Subcontractor did not forfeit its affirmative defense by not raising it until six weeks before trial on contribution claim. (KARNEZIS and CUNNINGHAM, concurring.)

National City Mortgage v. Bergman

Illinois Appellate Court
Civil Court
Mechanics Lien Act
Citation
Case Number: 
No. 2-09-0934
Decision Date: 
Wednesday, October 20, 2010
District: 
2d Dist.
Division/County: 
Lake Co.
Holding: 
Reversed and remanded with directions.
Justice: 
BURKE
Section 7 of the Illinois Mechanics Lien Act does not require the inclusion of a statement of the contract completion date on a lien claim in order to be enforceable. Mechanics Lien Act must be strictly construed, as mechanics' liens were not recognized at common law or in equity but exist only by virtue of statutes. (HUTCHINSON and JORGENSEN, concurring.)

Water Tower Realty Company v. Fordham 25 E. Superior

Illinois Appellate Court
Civil Court
Indemnification
Limitations
Citation
Case Number: 
No. 1-09-2943
Decision Date: 
Wednesday, September 29, 2010
District: 
1st Dist.
Division/County: 
Cook Co., 3d Div.
Holding: 
Affirmed in part, reversed in part; remanded.
Justice: 
NEVILLE
Plaintiff realty company sued Defendant company five years after Defendant completed construction of 50-story high rise building on its property, which was across the street from Plaintiff's building, for breach of agreement to indemnify Plaintiff for losses suffered due to the construction. Plaintiff claimed that Defendant used its property, during construction, such that it was impossible for Plaintiff to lease commercial space in its building. Indemnity agreement is broad enough to encompass both first-party and third-party claims. Ten-year limitations period for actions on written contracts governs, rather than four-year period for construction suits, as Defendant's potential liability emanates from its obligation under the written indemnification agreement, and is not related to Defendant's capacity as supervisor or manager of the construction. (QUINN and STEELE, concurring.)

Dorrnbos Heating and Air Conditioning, Inc. v. Schlenker

Illinois Appellate Court
Civil Court
Mechanics Lien Act
Citation
Case Number: 
No. 1-09-0076
Decision Date: 
Monday, July 12, 2010
District: 
1st Dist.
Division/County: 
Cook Co., 1st Div.
Holding: 
Affirmed.
Justice: 
PATTI
Court properly entered judgment in favor of HVAC contractor for medical office facility and surgery center on its mechanic's lien claim filed against physician and his wife, who was trustee of a trust which owned the property. HVAC company's claim was not barred by Section 6 of Mechanics Lien Act, as it was seeking to enforce its lien for work for which it had not been paid, and which was begun several months after the start of its initial work on the project; the work for which lien was asserted began within 3 years of when company ceased working on project due to non-payment. Three-year period of Lien Act commences with the beginning of work for which the mechanic's lien is asserted and not with the date upon which the contract for such work was entered into. Property owners failed to prove that company breached contract, as general contractor instructed company to commence its work prior to IDPH approval of design plans, and construction problems noted later were remedied and were described as not uncommon by IDPH architect. (HALL and LAMPKIN, concurring.)

LaSalle Bank National Association v. Cypress Creek I, L.P.

Illinois Supreme Court PLAs
Civil Court
Mechanics Lien
Citation
PLA issue Date: 
May 26, 2010
Docket Number: 
No. 109954
District: 
3rd Dist.
This case presents question as to whether trial court erred in apportioning proceeds of Sheriff's sale of piece of foreclosed property that gave only percentage recovery to two holders of perfected mechanics liens while permitting mortgagee of said property to be subrogated to status of mechanics lien claimant for monies it paid in construction and development costs through funding draws from trust. Appellate Court, in reversing trial court, found that claimants with perfected mechanics liens are not required to share sale proceeds with anyone except other claimants with perfected mechanics liens, and that while instant mortgagee could be subrogated in amount of $30,702 that it paid for third-party's perfected lien, it could not be subrogated for remaining $1.5 million in construction and development costs since instant mortgagee was essentially attempting to be subrogated for materialmen, who had been paid as work progressed, but who did not have perfected liens. (Partial dissent filed.)

Hensley Construction v. Pulte Home Corporation

Illinois Appellate Court
Civil Court
Construction Contracts
Citation
Case Number: 
Nos. 2-09-1140 & 2-09-1141 cons.
Decision Date: 
Friday, March 26, 2010
District: 
2d Dist.
Division/County: 
Kane Co.
Holding: 
Reversed and remanded.
Justice: 
McLAREN
Plaintiff, an underground utility business specializing in installation of water and sewer lines, sued residential construction businesses for non-payment. Trial court ordered construction businesses to pay money into escrow account pending final resolution of cases. Plaintiff requested only monetary relief, thus injunctive relief inappropriate as an improper prejudgment equitable attachment. Equitable attachments are prohibited in Illinois except where claimant has interest in specific funds held by debtor, which was not the case here, as funds had no connection to underlying dispute.